Overhaul Process
6 Steps of Pre-work Survey and Documentation
After going through the 6 steps of Pre-work Survey and Documentation above, the next step is to shut down the Power Generating Module for 9 -12 working days without Diesel Engine Overhaul or 21-28 working days include Diesel Engine Overhaul depending on the site accessibility to:-
(A) | Change generator for service exchange | Read More |
(B) | Replace all wear-and-tear components in diesel engine and Stromag Coupling on diesel engine crank shaft | Read More |
(C) | Replace Induction Coupling with service exchange | Read More |
(D) | Replace Free Wheel Clutch with service exchange | Read More |
(E) | Refresh key components of control panels | Read More |
(F) | Service Main power board (main breakers) | Read More |