Regional, Blog

FAT Passed. Site Failed. The Commissioning Gaps That Still Cause Downtime

Engineers commissioning critical power systems with UPS and switchgear in a data centre environment

A signed FAT certificate is a meaningful milestone. It confirms that a piece of equipment was built to specification, performed under controlled conditions, and met the manufacturer's defined test criteria. For complex power systems — generators, UPS, DRUPS, switchgear — that is not a small thing.

But it is not the same as site readiness.

The gap between equipment-level performance and system-level commissioning is where projects in Southeast Asia still run into trouble — not because the equipment was wrong, but because the conditions, interfaces, and integration that only exist on site were never fully tested before handover.

This article covers five commissioning gaps that appear repeatedly across data centre and critical infrastructure projects in Singapore, Malaysia, Indonesia, and beyond — and why they tend to emerge even on well-managed projects.

Related resource: Critical Power Tender Documentation: A Readiness Guide for SEA Projects

 
 

Why a Successful FAT Doesn't Guarantee Site Readiness

Factory acceptance testing is designed to verify individual equipment performance under controlled, repeatable conditions. The environment is stable. Variables are managed. Load profiles are simulated. The test proves that the unit works as designed.

What it does not prove is that the equipment will behave correctly when installed within a larger system — connected to site infrastructure, interfaced with third-party controls, and commissioned under the actual loads and sequences that the facility will operate under.

Site conditions introduce variables that no factory test can fully replicate: actual cable lengths and their impedance profiles, real load behaviour from mixed equipment types, interface signals passing between vendors who may not have coordinated their configurations, and physical installation details that directly affect how a system performs. These are not edge cases. They are the normal reality of site commissioning.

A factory pass is a prerequisite. It is not a guarantee of system readiness.

 
 

Engineer operating generator control panel and monitoring power systems during commissioning

The 5 Commissioning Gaps That Still Cause Downtime

The following gaps are not theoretical. They reflect patterns that appear across real critical power projects — across different equipment types, project scales, and market conditions in the region.

 
01

When Site Interfaces Are Connected But Never Actually Verified

On-site scenario: Two separate vendors — the UPS supplier and the building management system integrator — each completed their own testing successfully. On site, when the systems are connected, the alarm signals fail to route correctly. Each vendor had assumed the other was responsible for configuring the interface points. Neither scope was wrong. Both were simply never tested together — until handover.
02

When Control Logic That Passed in the Factory Behaves Differently on Site

On-site scenario: The generator's AMF control logic was verified in the factory against a programmable resistive load bank. On site, the actual connected loads include variable-speed drives, UPS equipment, and cooling systems — each with different inrush profiles. The control sequence hesitates during transfer. Not enough to cause a full trip, but enough to exceed the transfer time written in the spec. A test that passed in the factory requires re-evaluation on site.
03

When Transfer and Failover Sequences Have Never Been Run Under Real Load

On-site scenario: The genset starts cleanly. The ATS transfers on time. On paper, the test looks complete. But the sequence was run with minimal connected load — not with the actual UPS, server equipment, and cooling loads energised. When the commissioning team returns for handover, a test under real load reveals a voltage dip during transfer that was never observed before. The root cause only appears when the full system is live.
04

When No One Can Agree on What "Pass" Actually Means

On-site scenario: Three stakeholders in the room at sign-off — the client's project manager, the commissioning engineer, and the main contractor's representative. The transfer time meets the spec value. But one party flags a harmonic reading that was not listed in the original acceptance criteria. Another references a manufacturer's recommended limit that differs from what was written in the ITP. The test ran successfully. Sign-off takes three more days while the teams align on what "pass" was supposed to mean from the start.
05

When Documentation Is Still Being Written During Handover

On-site scenario: The commissioning tests are complete. The system performs. But the as-built drawings still reference the original equipment models — two items were substituted during the project. The O&M manuals that arrived cover the original specifications. The handover meeting is postponed while the documentation team catches up. Two weeks of delay — not because anything failed, but because the evidence trail was not built alongside the project.
 
 

Why These Gaps Are So Often Missed on Real Projects

These gaps do not typically appear because project teams are careless. They appear because of how commissioning tends to be positioned and resourced within a typical project structure — and because of pressures that are common across the industry.

 
FAT treated as the main milestone

When the factory acceptance test becomes the defining event of a project, everything that follows — site installation, interface verification, integrated testing — gets compressed into a smaller window with less scrutiny. A clean FAT certificate creates confidence that has not yet been earned at the system level.

Rushed project timelines

Commissioning is often the last planned activity and the first to lose time when earlier phases overrun. The result is a compressed window where teams are executing tests and chasing documentation simultaneously — under pressure to hand over on a date that was set before the site realities were fully understood.

Fragmented responsibilities

When multiple vendors, subcontractors, and site teams are involved, commissioning tasks can fall between ownership gaps. Each party assumes another has covered a step. Interface points between systems — which require coordination across scopes — are particularly vulnerable to this pattern.

Late-stage issue closure

Outstanding items — punch lists, unresolved RFIs, configuration changes — are carried into the commissioning phase rather than resolved before it begins. When issues surface during testing, the team is simultaneously trying to close earlier actions and validate the system, which compromises the reliability of both.

Documentation handled too late

Test records, as-built drawings, and handover documents are often treated as a post-commissioning task rather than something built concurrently with the project. When documentation is assembled at the end, errors, substitutions, and gaps in the evidence trail become difficult to reconstruct accurately under time pressure.

 
 

Integrated critical power infrastructure including UPS, generators and monitoring systems in a data centre

What a Thorough Commissioning Process Should Actually Cover

Addressing these gaps does not require a fundamentally different approach to commissioning. It requires that certain fundamentals are agreed, documented, and in place before testing begins — and applied consistently across the full scope of integrated systems, not just the headline equipment items.

 

Clear witness points

Hold and witness gates defined before testing begins — so every sign-off is planned, not negotiated on the day of the test.

Agreed pass/fail criteria

Acceptance standards written down and agreed by all parties before testing starts — not interpreted differently at sign-off by different stakeholders.

Integrated system testing

Systems tested together — not in isolation — under conditions that reflect real operational sequences, including transfer, failover, and restore scenarios with actual connected loads.

Evidence tracking throughout

Test records built concurrently with commissioning activities — not assembled retrospectively under time pressure at the end of the project.

Handover document control

As-built drawings, O&M manuals, test reports, and close-out documentation prepared and reviewed before the handover date — not issued as a post-commissioning chase.

At PPG, every commissioning process is tailored to the specific project — because requirements, interfaces, and acceptance criteria are never identical across two sites. What remains consistent is the discipline: testing evidence is built alongside the project, not assembled at the end of it.

   

Need a more structured way to review commissioning readiness?

We have developed a practical toolkit covering the full commissioning evidence cycle — from FAT witness checklists and SAT site verification through to integrated system testing, evidence tracking, and handover document control.

  • FAT witness checklist and sign-off gates
  • SAT site verification framework
  • Integrated system testing (IST) evidence tracker
  • T&C sign-off and handover document control
   

A Pass Should Be the Start of Confidence — Not the End of Questioning

A successful FAT tells you something important. It confirms the equipment was built correctly and performed under verified conditions. That matters — and it is a standard PPG upholds as part of every project, including bringing clients to witness testing at the manufacturer's facility.

What a FAT does not tell you is whether the system is ready — ready to transfer under real load, ready to interface reliably with every connected component, and ready to be handed over with documentation that the operations team can actually use from day one.

The projects that avoid commissioning surprises are not necessarily the ones with the most rigorous factory testing. They are the ones where site readiness is treated as a separate, structured process — with its own witness points, its own evidence trail, and a shared definition of what passing actually means before the first test is run.

Every project is different. The standard for readiness should never be.

 
COMMISSIONING TOOLKIT

Download the Commissioning Evidence Pack for critical power projects